China order calendar 2027: when to order for Christmas and summer
The best time to order in China in 2027 is calculated by working backwards from your target delivery date: allow eight to fourteen weeks depending on the product, the production lead time, quality control and the transport mode, while avoiding the year's two big shutdowns, Chinese New Year and the October Golden Week. This article gives the 2027 Chinese holiday calendar, a month-by-month buying calendar for Christmas, summer and back-to-school, and the trade shows to schedule into the year.
When to order in China in 2027: the method
An order date is derived from a delivery date, not the other way round. Set the date by which the goods must be available for sale, then subtract the actual transport time, the pre-shipment inspection and the production lead time quoted by the factory. Whatever day is left is your order deadline.
Two periods complicate this calculation in China in 2027: Chinese New Year, which shuts down part of the industry for several weeks at the start of the year, and the October Golden Week, which saturates freight capacity just before it closes. A calendar that ignores these two windows always slips from one season to the next.
- Target delivery date minus transport time, minus quality control, minus production, equals the order deadline
- Add a safety margin of two to three weeks around Chinese New Year and the Golden Week
- Always confirm the actual closure date directly with your chosen factory: it varies from one workshop to another
The Chinese holiday calendar in 2027
The official calendar of Chinese public holidays for 2027, with its make-up working days, had not yet been published at the time of writing. The official notice from the State Council is generally released at the end of the preceding year: the one for 2026 was published on 4 November 2025. The dates below are therefore calendar dates calculated in advance for the lunar festivals, not officially decreed days off. Two dates stay fixed every year, with no lunar calculation: 1 May and 1 October.
- Chinese New Year (Spring Festival, Year of the Goat): Saturday 6 February 2027, provisional date, official holiday not yet decreed
- Qingming (Tomb-Sweeping Day): Monday 5 April 2027, calendar date
- Labour Day: Saturday 1 May 2027, fixed date, make-up working days not yet decreed
- Duanwu (Dragon Boat Festival): Wednesday 9 June 2027, provisional date
- Mid-Autumn Festival: Wednesday 15 September 2027, provisional date
- National Day (Golden Week): Friday 1 October 2027, fixed date; a holiday period from 1 to 7 October 2027 is expected by analogy with previous years, not yet confirmed by decree
Read next Chinese New Year 2027: factory calendar and import timeline
Why a factory shutdown lasts longer than the public holiday
Around Chinese New Year, the official public holiday says nothing about a workshop's real schedule. Most factories close three to four weeks before the official date, to give workers time to travel, and ramping back up to full speed takes several more weeks afterwards: the total disruption often spans six to eight weeks. A share of the workforce, estimated at close to a third by specialised logistics guides, does not come back, forcing some factories to recruit and train new teams in early February.
Around the October Golden Week, many factories close or scale back activity, and operations officially resume only on 8 October, with freight normalising taking further time beyond that. On the already-confirmed 2026 calendar, only three working days separated Mid-Autumn (25 to 27 September) from the Golden Week (1 to 7 October); in 2027, the gap between the provisional Mid-Autumn date (15 September) and National Day leaves more margin, to be confirmed once the official calendar is published.
Read next Verify a Chinese Factory: License, Capital, and Visit
The five-step countdown before a shutdown
Faced with a known deadline, a standard preparation timeline recurs year after year among freight professionals. It is read in weeks before the shutdown, not before the final delivery date.
- Six to eight weeks before: confirm production needs and the required stock level
- Four to six weeks before: request freight rates and book sea or air space
- Three to four weeks before: verify the actual date the cargo will be ready
- Two to three weeks before: finalise quality control and shipping documents
- Final week: reserved for cargo already confirmed and ready to ship
Read next Requesting a quote from a Chinese factory: the well-made RFQ · RFQ: Meaning, Contents and the Difference From RFI and RFP
The month-by-month buying calendar in 2027
China-Europe sea freight is one of the most decisive variables in an order calendar: port-to-port transit ranges from 25 to 45 days from Shenzhen, often 35 to 55 days from Shanghai or Ningbo, due to the current rerouting around the Cape of Good Hope. This benchmark builds the calendar season by season, around the year's two Chinese shutdowns.
- January: last window to finalise production before Chinese New Year, negotiations already closed
- February: many workshops actually closed around 6 February; a good period for scouting, as factories are less busy
- March: ramp-up after Chinese New Year; window to launch summer orders (June-July)
- April-May: the Canton Fair spring session, for sourcing and setting the season's prices
- June: last reasonable window for back-to-school (August-September), given 25 to 55 days of sea transit depending on the port
- July-August: the window to favour for Christmas; by sea, six weeks from the south, seven from central China, eight from the north are added to production time
- September: last window for Christmas via sea freight before Mid-Autumn (15 September, provisional) and the Golden Week; beyond that, air freight becomes necessary
- October: Golden Week (1 to 7, expected, not confirmed) and the Canton Fair autumn session; freight capacity saturates just before, book early
- November: gradual normalisation after the Golden Week, last Christmas orders via express
- December: preparing specifications for January-February 2028, ahead of the next shutdown
Read next Sea freight from China: FCL or LCL, costs, transit times and break-even point · Air freight China: when to choose it and how it is priced
Trade shows to put in your 2027 calendar
The Canton Fair remains the most structuring event for sourcing new suppliers: spring session from 15 April to 5 May, autumn session from 15 October to 4 November, each in three phases. This calendar, announced for autumn 2026, is carried over by analogy for 2027; the organiser had not yet published official confirmation at the time of writing. Check the exact calendar on the official site before booking a flight or hotel.
The spring session prepares summer and back-to-school orders, the autumn session prepares the following year's orders.
Read next Canton Fair user guide: dates, phases, and buyer badge in Guangzhou
The mistakes that cause a deadline to be missed
Planning around the official public holiday alone, without the factory's actual shutdown, which often starts several weeks before and continues after. Assuming a single transport lead time: depending on the port and route, sea transit to Europe can double, from 25 to more than 50 days.
Booking freight at the last minute before the Golden Week or Chinese New Year, when demand concentrates into a few weeks. Never asking the factory directly for its closure date and reopening plan, relying instead on a generic calendar rather than written confirmation.
Read next Hidden import costs: the fees beginners forget to budget for
What Sorva does for you
Sorva builds the countdown for every order from the chosen factory's actual closure date, not the theoretical date on the Chinese calendar. Our Chinese-speaking team in Guangzhou confirms directly with the workshop its closure date, its order deadline and its reopening plan.
For an order timed to a season, our full supplier search frames the production calendar from the outset; for a calendar that repeats every year, a monthly follow-up keeps an eye on factory deadlines. In most cases you open a file, we negotiate the merchandise on your behalf and we take a commission on its ex-works value.
Remember that the order date is calculated by working backwards from your target delivery date, not from the Chinese calendar alone: allow for sea transport (25 to 55 days depending on the port), production, and a margin around Chinese New Year and the Golden Week. First step: note down your target sales dates for 2027 now, and ask each factory for its own closure date.
Plan your order before the factories close
Frequently asked questions
01When should you order in China to receive goods in time for Christmas 2027?
02What is the date of Chinese New Year in 2027, and is it already official?
03How long does the shutdown of Chinese factories around Chinese New Year really last?
04When should you order to be delivered before summer 2027?
05Is the 2027 Chinese public holiday calendar already published?
06Should you factor the October Golden Week into your order calendar?
07What are the Canton Fair dates in 2027?
The service that matches
- CommissionVolume commissionYou open a file, we find and negotiate the factory. We are paid only on the goods you order.€150file opening feeView service
- One-off serviceSupplier search · fullA bidding round run for you, one priced grid, samples in your hands.€279per productView service
- Ongoing supportMonthly managementA buying programme run continuously, with two inspections included each month and a dedicated contact you can reach.€490per month, excluding VATView service
- PackageLevel II · Produce and deliverEverything in Level I, plus own-brand production, factory inspections, negotiated freight and DDP delivery.€1,590deposit on ordering, balance by milestoneView service